Phase 1

Phase 1 includes design in 2018 and through 2019. This is the initial $10 million being programed.
 Construction work at the waterfront along the green space at Arnolds Park and along the waterfront in front of the roller coaster, along with the work along the promenade to the Emporium will be under construction this spring and fall of 2019.

The work on Lake Street in front of the Pavilion and the new Roof Garden building, will not start until the Roof Garden is complete, due to coordination of the work at the Roof Garden and complexities of coordinating that construction. This is likely to start in the fall of 2019 and be completed in the Spring of 2020.